Plus One

control-plan.csv · 619 B · commit #1 · Nov 1, 2026

SHA-256 72507619c19ff1f8adf32403e263747606364a1f13fd2e4a6168e4a8e3576cc4

stationcheckmethodreaction
S1stake pull-off, first five each shiftpush-out testerstop and reset the staker
S3torque and angle window, every screwdriver controllerreject the unit to rework
S4bead present and placed, every unitbead camerawipe and redispense
S52 N tug after mating, every unitseating toolreseat once, then reject
S6close force curve and magnet polarity, every unitpress monitor and gaugereject the unit
S7flash hash, unit ID once, calibration limitstest PCreflash once, then reject
S8full functional test and QR read-backfunctional testerreject to failure analysis

7 rows.